Appearing virtually before the Commonwealth Utilities Corp. board Thursday, Eastern Power Solutions Chief Executive Officer Daniel Myung said the company has started recruiting between 100 and 150 workers and intends to hire residents from Saipan, Tinian and Rota as it advances development of its renewable energy projects across the Commonwealth.
Responding to concerns raised by CUC board member Miranda Manglona about equitable hiring among the islands, Myung said the company plans to recruit locally on each island and establish training programs in Saipan, Tinian and Rota.
"We would prefer to have Rota projects done as much as possible through Rota residents, and Tinian projects done through Tinian residents," Myung said. "Rather than transporting our workers back and forth, it makes sense to work with the local people there."
Myung said Eastern Power Solutions has already hired key personnel, including a chief engineer, and recently advertised positions as it ramps up staffing for project implementation.
The company is also moving forward with environmental reviews and financing requirements. Myung said EPS has initiated the National Environmental Policy Act process with the U.S. Department of Agriculture, completed preliminary surveys and is finalizing documentation for a USDA loan.
According to Myung, the company expects to complete the solar generation component of the project by December 2027, place the battery energy storage system into service by September 2028 and fully commission the integrated system by December 2028.